Phase III Street Project
The City of Tracy Phase III Street project is a $21 million reconstruction of water, sanitary sewer, storm sewer and streets throughout the city. The project is ongoing over multiple years beginning in 2019 and continuing through 2023. Currently work has been completed for phase 3A-1. The Pond Decommissioning Project and 3A-2 will be complete in the Spring of 2023. Future phases in 2023 include the reconstruction of Center Street between Highway 14 and the South Street starting in May of 2023, and Summer of 2023 there will be a Cured in Place Pipe Lining Phase which includes multiple areas throughout the City. These projects are funded through a combination of USDA and state PFA Clean Water Grants, a long-term loan from Rural Development at the US Department of Agriculture, and general obligation bonds issued by the city in 2019.